In some ways, the proliferation of high-speed automation over the past decade has created a more even playing field in the large-scale commercial insulating glass (IG) fabrication market. With widespread automated IG lines, capacity and volume are no longer in question, meaning fabricators must find new ways to differentiate themselves with services.

That’s especially true in a softer marketplace like the one we’re currently experiencing. Selling, producing and shipping as much glass as capacity allows may not necessarily be an available strategy. However, ensuring your lines stay busy involves committing to the highest quality, service and internal efficiency levels.

To those ends, logistics and communication become more critical; considering how we’re sourcing raw materials, ensuring we’re doing that efficiently and at optimal volumes to fulfill your current pace of orders is crucial. Here are a few things to think about.

Optimizing the Flow of Production

Proper product mix handling is essential to getting the most out of any automated line. For example, many architectural IG units are made with tempered or heat-strengthened glass; if IG lines are producing beyond the capacity of your tempering furnaces, bottlenecking is inevitable. Differences in coatings, glass thickness and several other variables mean differences in tempering cycling time and alternate configurations. That means optimizing tempering furnace capacity to suit your current order volume.

Keeping the optimal flow in your product mix also involves having a good grasp on lead times and closely tracking customer orders at the beginning of the process. This is especially critical in softer market conditions, where meeting customer delivery expectations is vital to maintaining satisfaction. All the little details that make up the big picture make all the difference.

An Eye on the Jobsite

Getting orders out on time, on-spec, in the right places and efficiently can be challenging no matter the market conditions. It requires close collaboration with and high levels of service for your customers.

Another example: Consider a high-rise architectural glass project in a dense urban environment, where storage for building materials will be tight. In these small footprint jobsites, delivering all the glass necessary for the job at once is impossible, requiring a more nuanced approach to delivery and the logistics to make it happen. Some glass can be staged onsite, but not all of it, and storing large quantities of glass at your plant may create a headache. Making sure your production flow is optimized here can help.

It’s also important to remember that jobsite construction delays are inevitable. What happens if there’s a two-week delay and several of your glass racks are stuck at the site? These sorts of contingencies have always existed in our industry. Properly managing them requires ensuring you’re in tune with all your customers, setting the right expectations and maintaining open lines of communication are essential here.

Juggling Different Projects

Sequencing the deliveries for a large-scale architectural project must also be balanced with the other projects going on simultaneously, whether they’re quick storefront turnarounds or other smaller commercial jobs.

Considering that many architectural projects require customized sizing and other unique attributes, it’s not a matter of simply churning out uniform IGUs for all work; different shapes and sizes must be accounted for in your production schedules, along with more uniform jobs and having a system in place to compensate is critical.

Providing excellent customer service and outstanding quality consistency can be a key differentiator under softer market conditions. Unless we’re taking care of the details from beginning to end, problems will arise. Finding your balance, identifying the right mix of products and the correct production rate are the only ways forward.