Contracts, Provisions and Legalese, Oh My: Delving into the Dangers of Defects and Delays

By Karalynn Cromeens

Sometimes working in the glass industry can feel like that scene in the Wizard of Oz, when Dorothy, Scarecrow, and the Tin Man are walking through the dark forest, and they have no idea what could be hiding in the woods. That is how it feels when you have to sign a contract. You need the work, so you sign the contract, but you have no idea what sneaky clauses, hidden provisions, and convoluted legalese could be buried in the document that could come back to bite you. My job is to explain what elements of your contract could be dangerous so you can negotiate and reduce the risk of your contract, putting you in the best possible place to defend yourself if something does jump out at you.

Defective Work

First, what is considered a “defect” under the terms of a glazing contract isn’t what common sense may lead you to believe. When hearing the word “defect,” most people think of something that does not work properly or is broken. However, under a construction contract, a defect can be something that works perfectly fine, but if not done exactly to the plans and specs, it must be redone. For example, say a painter is hired to paint the interior of an office building. It looks great, but it is the wrong color, so it must be redone. There was nothing defective about the paint or the work itself, but if it is not in accordance with the specs, it is considered defective work.

This is something to keep in mind when you get a notice of defect letter and are debating whether to make the repair or not. There may be nothing wrong with the work in your mind, and technically you may be right, but you were hired to do your work in accordance with the plans and specs, not to your satisfaction. If your work is not done in accordance with the parameters set by your contract, it is technically defective, and you are responsible for redoing the work. Even worse, if you do not respond to a notice of defect properly and quickly, you can risk termination from the project.

Delay Damages

One of the most important things to an owner is knowing when the project will be done. They want a known completion date so badly that they will charge a per-day penalty for the contractor not completing work on time. This is also known as “liquidated damages,” or more commonly, “delay damages.” Here is how it breaks down: the general contractor promises a completion date to the owner. The general contractor then gives each
subcontractor a deadline to complete their work and ensure the project is completed by the promised date. If the subcontractor does not complete its work by the scheduled date, liquidated damages will be charged to the subcontractor.

With the way most subcontracts are written, the glazing subcontractor would have to pay the general contractor liquidated damages even if the owner does not charge the general contractor with them. It’s important to do what you can to negotiate the subcontract so that you will only be responsible to the general contractor if the general contractor is liable to the owner for liquidated damages caused by your failure to complete the project on time. When you are asked to do additional work that is outside of the original scope, you must get a change order. If the additional work will take you extra time to complete, always list the extra time needed in your written change order before proceeding. Creating a paper trail and ensuring that the general contractor or owner understands that the new work will require your timeline to be extended is essential in avoiding delay damages.

You can walk through the dark and scary woods unafraid if you are prepared for whatever could jump out at you. Understanding the terms of your construction contract will give you lion-like courage.

Karalynn Cromeens, is the owner of The Cromeens Law Firm and The Subcontractor Institute in Houston. She has been a licensed construction attorney for over 16 years.